Construction of Huoshenshan Hospital in Wuhan, with 1,000 beds, was officially completed within 10 days of construction, on February 2nd, 2020.
Excavation started on January 24th
Construction officially started on January 25th
More than 300 prefabricated container-type stuctures were used.
By January 31st, 90% of the containers had been assembled into the construction area.
Medical equipment installation began on February 1st.
Construction was officially completed on February 2nd.
Location of Huoshenshan Hospital
Location of Huoshenshan Hospital (Before construction, Gaofen No. 2 satellite was taken on October 29, 2019)
Location of Huoshenshan Hospital (Before construction, Gaofen No. 2 satellite was taken on January 30, 2020)
Location of Huoshenshan Hospital (Before construction, Gaofen No. 2 satellite was taken on January 31, 2020)
Reporters were told that all medical equipment for the wards meet international standards.
All wards are negatively-pressurized with fresh air exhaust systems to ensure that the pressure in the wards is lower than outside so that the air within the wards is not discharged to the outside environment.